Albuquerque Marriott Pyramid North
310 guest room openings inside a property-wide modernization, delivered in three timed shipments.

Project Overview
Three shipments, each timed
to a construction milestone.
The Albuquerque Marriott Pyramid North underwent a property-wide modernization covering more than 1,100 openings. Forest Bright engineered and supplied the complete door systems — leaves, frames, and hardware, to a uniform specification and finish standard — for 310 guest room openings within that programme.
Storage on an operating hotel site is the constraint nobody budgets for, so rather than shipping the full quantity at once, the order was segmented into three shipments, each timed to a specific construction milestone. All three arrived on schedule and the on-site installation ran without interruption.
Scope of Supply
Forest Bright Supplied:
- 310 sets — of 20- to 90-minute fire-rated stile and rail wood doors, finished in white primer
- Knock-down primer hollow metal steel frames — assembled on site
- Complete hardware package — hinges, closers, door guards, viewers, smoke seals, kick plates, bottom seals, door stops